Resources
Catch up on the construction progress, the project's history, meeting materials, photos and more!
Construction Progress
Click or swipe to see recent construction photos of the expansion project.















Watch our Construction Progress Video
Documents and Presentations
Project History
The original Water Reclamation Facility was built and began operating in 1967. Various updates, improvements, and the creation of new buildings have progressed over the decades and now we are in the midst of a multi-year expansion.
-
1967
The original plant was built and began operating. -
1985
Tertiary and sludge storage upgrades were completed. -
1991
Grit and septage systems were improved. -
2003
The South Activated Sludge Plant, Sludge Dewatering Building, and administration buildings were constructed. -
2013
Algae control systems were improved -
2014
Post-aeration and UV improvements were completed, and a filter arm was replaced. -
2016
A Facility Master Plan was adopted. -
2019
Electrical upgrades were completed. -
2021
Boiler replacement completed. -
2022
Department of Agriculture and Natural Resources (DANR) Grant and loan from SRF awarded to City. -
2023
MIPS Facility Project and fencing improvements completed. -
2024
WRF Aeration Basin Clariflocculator completed. -
2025
Construction of building structures for liquids and solids handling. Begin installation of underground piping. We are Here -
2026
Aeration Basin, Secondary Clarifiers, Blower Building and Pump Building complete. -
2027
Finalize Solid Handling facilities and make reliability improvements to existing plant. Startup / Commissioning of South Plant. -
2028
Demolition of North Plant facilities and finalize civil / site work.